skip to Main Content
GSA Phoenix Professional Office Building
GSA Phoenix Professional Office Building

2010 – 2011

210,000 sq. ft., 5-story office buildng for Phoenix Federal Bureau of Investigation field office with vehicle bays, support spaces and 2-story parking structure.

Case Study

Dial Corporate Headquarters
Dial Corporate Headquarters

2008

Four floors of corporate offices and R&D on top of 3 garage levels, 730,000 sq. ft., LEED certified;

Intel “OC2, C3, C4, C6, C7” Support Facilities
Intel “OC2, C3, C4, C6, C7” Support Facilities

1990 – 2008

Various office support buildings totaling over 1,000,000 sq. ft. on 2 campuses.

Case Study

Papago Gateway Center
Papago Gateway Center

2007

Seven floors/250,000 sq. ft. with six-level parking structure; designed with an automatic exterior louver shade system for energy efficiency; design-assist project with a 16-month duration.

Cotton Center III
Cotton Center III

2007

45,000 sq. ft. shell and TI office building, LEED Silver certified.

Case Study

North Central Association CASI
North Central Association CASI

2004

20,000 sq. ft. office, one of the first LEED Gold certified buildings in Arizona.

Wells Fargo Ocotillo Campus
Wells Fargo Ocotillo Campus

2003

(2) 3-story buildings, 550,000 sq. ft. on 60 plus acres; 12 month construction duration.

American Express North Phoenix Campus
American Express North Phoenix Campus

2001

(2) 3-story office buildings, 15KV loop distribution and utility paralleled generator plant, 500,000 sq. ft.; 20 month duration.

Case Study

Phoenix Plaza Campus
Phoenix Plaza Campus

1989

(3) high-rise buildings, highest 25 stories, 1,500,000 sq. ft. mixed use office;18 month duration.